Internal Coating Rehabilitation
|
Internal pipeline coating in the field as well as internal coating rehabilitation are a relatively new but extremely effective solution. |
||
![]() |
||
|
scheme of internal coating rehabilitation |
||
![]() |
Pig launchers and receivers are used for internal coating application, and they can be spaced as far apart as 48km. |
![]() |
||
|
pig launcher |
pig receiver |
|||
|
Work is done in several stages: |
||||
![]() |
1. internal surfaces |
![]() |
||
|
placing of cleaning pig in pipe |
cleaning pig after passing through the pipe |
|||
![]() |
2. chemical cleaning and preparation of the surface is carried out to improve the coating adhesion:
|
|
|
placing of drying pig |
||
![]() |
3. application of internal coating by deposition of a special coating solution contained between the second pig from stage 2, and a third pig. |
|
|
placing pig in pipe |
||
|
As a result, not only is the service life of the pipeline increased, |
![]() |
|
|
rehabilitated internal coating |
|
Over the past few years, low–pressure lines (mostly in city infrastructure) have been successfully repaired |
||
![]() |
![]() |
The polymer pipe is slightly smaller in diameter than the existing pipe. Tightly gripping the new line, the old one now serves as mechanical protection. The insignificant decrease in diameter is compensated |
|
a polymer pipe relining an old pipe |
||
|
If the existing pipe is made of material that can be destroyed by specific vibrations, the polymer pipe replaces the old pipe, which it destroys as it is pulled through. |
![]() |
|
|
replacing pipe by destruction of the old pipe |
||
|
Trenchless methods are used on these jobs, which is important for cities and busy highways. |
||